- We will shortly be carrying out carriageway & footway improvements along Church Street, Wellington
- Works will be completed by Balfour Beatty and specialist sub-contractors Quantum Traffic Management, GN Groundworks, Prysmian, WJ Lining & Tarmac.
When are we planning to deliver this work?
The work is due to take place on 06/01/25 and be completed by early May (weekdays only) weather permitting. Please see below the traffic management phasing for the duration of these works:
Phase 2 – 06/01/25-19/01/25 – 24hr one-way closure
Phase 3 – 20/01/25-02/02/25 – 24hr one-way closure
Phase 1 – 03/02/25-23/02/25 – 24hr road closure
Phase 4 – 24/02/25-09/03/25 – 24hr one-way closure
Phase 5 – 10/03/25-23/03/25 – 24hr one-way closure
Phase 6 – 24/03/25-06/04/25 – 24hr one-way closure
Phase 7 – 07/04/25-27/04/25 – 24hr one-way closure
Phase 8 – 28/04/25-04/05/25 – Night closures (including Vineyard Road), 19:00-05:00
For additional information and to find a copy of the traffic management plans for these works, please click the following link: https://www.telford.gov.uk/info/21936/wellington_public_realm
These works are being delivered as part of the Council’s investment programme to ‘Protect, Care and Invest to create a better borough’. Over the next four years, over £40m is being invested to keep neighbourhoods safe, clean and well connected. The ‘Pride in our Community’ Highways Capital Programme will deliver improvements to infrastructure including roads, footpaths, sustainable transport, road safety, street furniture, drains and structures. Our highways vision is to ‘Keep Telford Moving’ and in 2024/2025 we will invest £9m to deliver a number of improvement schemes across the borough.
Balfour Beatty will be the lead delivering this work in partnership with the Council and our details are below, for any questions or queries relating to this scheme please contact us at our highways hub:
TelfordHighways@balfourbeatty.com
For more information about the Council’s Pride in Our Community programme please visit www.telford.gov.uk/pride. The full list of works planned for your area can be found on the projects page.
Kind Regards
Balfour Beatty – Telford Highways Hub
Granville House Depot
St Georges Road
Donnington
Telford
TF2 7RA
E: TelfordHighways@balfourbeatty.com
For all latest Council news visit the newsroom; follow us on Facebook and Twitter